Sunday, June 25, 2023

'Smart City' another year 'slow'

Smart City: A new deadline of June 30, 2024; Works worth ₹300 crore in progress

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

BENGALURU: The deadline for the completion of the Bengaluru Smart City project has been delayed by another year and works worth around ₹300 crore are still in progress.

The officials of the Smart City project were promising that all the works would be completed by June 23 and there would be no delay. However, there are still a couple of days left for that deadline, but seven works are still going on. As one more year has been given, the possibility of speeding up the works has diminished.

The capital Bengaluru was included in the 'Smart City Project' after a lot of struggle. Icon works were expected to take place in the city. However, more than half of the money was spent on Tendersure. Out of 32 roads, 5 roads are still not completed.

The work of providing state-of-the-art auditorium and other facilities in the Jawaharlal Nehru Planetarium is still progressing. Although it is said that three quarters of the work has been completed, the actual picture is different. The redevelopment of the Economic center of the K.R. market has been going on for years. The chaos at the place is a mirror of the slow pace of work there.

 The much awaited Integrated command and Control Center (ICCC) is a project to provide security to the city, provide solutions to traffic, pedestrian and grievance issues at a single platform. It is still in its early stages. Car parking work has not started at Gandhibazar.

 As the deadline for smart city projects has been extended by another year, there will be further delay in the work. There will be further delay in getting the facilities to the citizens.

Almost getting over..

Smart city projects are almost complete. Some works have been delayed due to local issues. Everything will be completed as soon as possible. New projects cannot be taken up. Sushilamma, the managing director in charge of the Smart City project, said that the already planned works will be completed.

 44: Total projects

 37: Completed works

 7: Balance projects

₹928.57 crore: Cost of Smart City Project works

₹629.73 crore: Amount of completed works

₹298.84 crore: Value of unfinished works in progress


Works in progress

Work; Cost; Physical progress

Smart Tendersure Road – Millers Road, Cantonment Road, HKP Road; ₹41.40 crore; 95 percent

Smart Tendersure Road – Avenue Road, Reinus Street; ₹34.21 crore; 92 percent

Auditorium block at Jawaharlal Nehru Planetarium; ₹42 crore; 73 percent

K.R. Market – Redevelopment of meat market; ₹6.70 crore; 80 percent

K.R. Redevelopment of Market- Financial Centre; ₹40.05 crore; 85 percent

Integrated Command and Control Center (ICCC); ₹112.35 crore; 85 percent

Multi-storied car park at Gandhibazar; ₹22.13 crore; 0 percent


ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...

ಬೆಂಗಳೂರು ‘ಸ್ಮಾರ್ಟ್ ಸಿಟಿ’ ಮತ್ತೊಂದು ವರ್ಷ ‘ನಿಧಾನ’



Thursday, March 9, 2023

Smart City 'Amrita Utsav' at Balabhavan

Smart City: BBMp students enjoyed 'Putani Train' and boating at Balabhavan

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

Bengaluru: As part of the Women's Day celebrations, the students of BBMP School enjoyed the fun of the redesigned 'Putani Train' at the Bala Bhavan at the 'Amruta Utsav' organized by the Bengaluru Smart City Mission.

The 'Putani Rail', which has been suspended for many years, has been redesigned in the Smart City project. It has not yet been inaugurated. For the first time, children were given the opportunity to walk in it on Wednesday.
 As part of Azadi Ka Amrit Mahotsav, Smart City Mission has organized 'Amrit Utsav' events till June 30. The objective of this festival is to empower women and children. In this context, Smart City projects were introduced to 250 students of BBMP's Vijayanagar, Srirampura, Mattikere Girls' School in a 'Smart Tour', said Sushilamma, Joint Managing Director of Smart City Project.

In Smart Tour, students visited to Integrated Command and Control Center (ICCC) at BBMP, Jawaharlal Nehru Planetarium and train ride, was conducted at the at Cubbon Park, Bala Bhavan. The students also enjoyed the newly constructed boating facility, she said.

 Inauguration this month?: 

Almost all the works in Cubbon Park and Bala Bhavan have been completed. By the end of this month, it is planned to open all the facilities including the Putani train and boating to the public. Sushilamma said that Chief Minister Basavaraja Bommayi will launch soon.