NAMBIKE NAKSHE (Building plan)not found in time limit

BBMP: Approval only after going to AROs office

NAMBIKE NAKSHE not found in time limit

  •  More than 50 percent applications are pending
  •  Excessive delay in East, West, South zone
  •  The original purpose of the project failed


Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್ 

 Bengaluru: The objective of the 'NAMBIKE NAKSHE' project, which started with the slogan of providing a map for the construction of residential buildings in a single day, has failed. Citizens do not get the map within the time frame, and the wandering to the BBMP offices has not stopped yet.

 Under the concept of 'Brand Bangalore', the 'NAMBIKE NAKSHE- Nimma Mane Nakshe Nima bagilige' scheme to get building plans without going to the BBMP office was practically successful in Rajarajeshwari Nagar and Dasarahalli zones.

 Deputy Chief Minister D.K. Shivakumar had extended this scheme to all sectors from September 2. Even after almost two months, the plan has not materialized. Plan not available online. A plan is available only if you go to the office of the revenue department officials and wander for a while.

 As per the 'Nambike Nakshe' scheme, approved map should be available within 15 days if all documents are ready for residential buildings up to 50 ft x 80 ft size. The 'temporary plan' should be available on the day of application. All this process has to be done online and BBMP staff cannot visit the office. But all this remains in the project's mission statement.

 If you apply for the plan online, the process of the city planning authorities will be completed quickly. But the revenue officials are delaying. Check the documents in the revenue department, if they match the map should be approved. "Assistant Revenue Officers (AROs) who do not follow this, want the owner or engineer to 'contact them' like before," complained Raghunath, owner of Padmanabhanagar.

 "Once a system is successful in practice, it should be fully implemented online. Although the time frame is said to be approval of the plan, it is not fixed for the AROs. If they do not approve within seven days, the approval should be automatic. But, that process is not going on,' alleged Engineer-Architect Ramesh.

 The process of providing e-khatha for all properties in the city is underway. Besides, work of revision of voter list is also going on. Thus, the process on the 'Nambike Nakshe' is slowing down," explained AROs who did not want to be named.

 'There is no difference from before'

 Although the new scheme has been implemented, there is not much difference from the old system. As the slogan of 'Nambike Nakshe' suggests, 'temporary plan' is not available in a day. They made it as if there was no choice. As before, AROs should be visited frequently in their office, during their time. Architect-Engineer Sarvottam shared his experience saying that the statement 'You cannot go to BBMP office' has not been implemented here. Citizens' wandering has not stopped.

 'Not yet full automated'

 Automatic plan approval under the 'NAMBIKE NAKSHE' scheme for buildings has not been fully implemented. The approval of the plan is done only after the approval of the Assistant Revenue Officer (ARO) after completion of the process. It is held that there may be problems if there is an automatic system at the initial stage. However, it is true that the approval by AROs is getting delayed. At their stage, there are many pending applications or files,' informed the senior officials of the Town planning department.

 Application status of 'NAMBIKE NAKSHE'

 (From September 2 to October 28)

 Zoning; Application Receipt; Approval

 East; 126; 17

 West; 145; 50

 South; 215; 30

 Bommanahalli; 250; 64

 Mahadevpur;78;35

 Yalahanka; 107; 60

 Rajarajeshwari Nagar;707;480

 Dasarahalli; 49; 37

 Total; 1617; 773