BBMP gearing up for tree census

 Report for the end of March 2024 | Enter the information along with the variety in the mobile app

 BBMP gearing up for tree census, data collection



Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

  •  ₹3.74 crore Total cost of logging
  •  ₹46.80 lakh Cost of enumeration in each zone
  •  20.80 lakh Estimation of trees in the city
  •  2.60 lakhs Approximate number of trees in each zone

 Bengaluru: BBMP has finally decided to conduct a census of trees in the city and plans to complete the census by the end of March 2024. Comprehensive information including tree-plant picture, species will be recorded in the app.

 The tree census will be done on the mobile app prepared by the Karnataka State Remote Sensing Application Center (KSRSAC). BBMP forest department has invited tenders for tree census and data collection on August 7. Separate tenders have been called for eight zones and the tender will be finalized on 25th. Once the subsequent processes are completed, the census is scheduled to be completed by the end of March 31, 2024.

 A census of the trees in Bangalore should be made public. In 2019, the High Court had instructed the BBMP that the census process should be started in three months. After four years, BBMP has started a tree census.

 The Census piloted by BBMP is in six volumes and BBMP currently has information on only 46,593 trees.

Also read.. ಹಸಿರು ನಗರಿಯಲ್ಲಿ ಗಣತಿಯಾಗದ ಮರಗಳು

 According to the Tree Preservation Act, a census must be done. Although the High Court gave an order in 2019, the tree census has not started. BBMP officials were giving some reasons,' said Dattatreya T. Devere of Bangalore Environment Trust.

 The census of trees is being carried out on priority basis. Once we get this number, it will help us for further planning. We also publish information about each tree on the website. Information about how many trees will be felled and where for which projects will be available. Besides, the details of newly planted saplings will also be published,” said Swamy, DCF, Forest Department, BBMP.

Barcode Board

 Botanists will be in the surveying team. A census of all the trees and plants with a diameter of 5.5 cm or 1 meter in height will be collected. A number is entered on each tree during the census. After all this report is prepared, the image of the tree, its number along with its age, species information can be obtained through barcode. A barcode board is placed on the trees that can be seen standing on one side of the road. Through this, complete information about the trees in their area will be available to the public.

 '2 trees for every house'

 Swamy, Deputy Conservator of Forests, BBMP, said that by implementing the rule that every house in the city should have two trees, everyone will be encouraged to plant and grow saplings.

 According to the rules of the Karnataka Tree Preservation Act, there should be two trees per plot of 222 square meters (2,389 square feet) of houses and buildings in urban areas. 892 square meters (9,600 square feet) of building-sites should have three, then four trees in area. Industrial and Institutional premises should have 25 trees per hectare. He said that it has been decided to implement this rule.

 In community housing area (gated community) two saplings per house are mandatory. Then it will be implemented everywhere in the city. He informed that all measures will be taken to increase the amount of green cover in the city.

 In Bengaluru, a city with a population of 1.30 crore, there is one tree for every seven people. In Chandigarh and Gandhinagar there are four plants per person, in Nashik there are two plants per person,” said Prof. Indian Institute of Science. T.V. Ramachandra informed.

ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...



Friday, October 6, 2023

Jayanagar got 'Commercial Area' feather

 Immovable property: Value appreciation for peripheral property, agricultural land as per revised guideline value

 Sadashivanagar has 'High Value', Jayanagar got 'Commercial Area' feather



Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

BENGALURU: Sadashivnagar is one of the highest value localities in the city with a reputation as a prestigious residential area. surpassing M.G. Road, Cunningham Roads, Jayanagar has become the most expensive 'Commercial Area'.

 As per the Revised Guideline value of Assets effective from October 3, the value of residential area is highest in Sadashivnagar. Sankey Road, Sadashivnagar properties are priced at ₹3.02 lakh per sq.m. In Acchaiah Shetty layout, the price is ₹2.96 lakh per sq.m., while in Palace Lower Orchards in this area, the rate is ₹1.43 lakh per sq.m. Assets on 11th Main Road, Jayanagar 4th Block fetched ₹2.76 lakh per sq.m, which is high in this segment.

 The guideline price for commercial plots from Cosmopolitan Club Circle to 11th Main Road in Jayanagar is ₹5.36 lakh per sq.m., which is the highest in the urban district. 5.03 lakhs in Jayanagar's 27th cross and 30th cross. 9, 10, Main road, 33rd, 36th, 46th Avenue, 100 Feet Road, South End, etc. The price of commercial plots in this vicinity ranges from ₹4.65 lakh to ₹3.65 lakh.

 ₹ 3.62 lakh per sq.m for commercial plots in prestigious commercial hubs of the city such as Cunningham Road, MG from Kasturaba Road to Trinity Circle. ₹.3.15 lakh for roadside commercial plots. Beyond the value of both these areas, Jayanagar is the highest value 'Commercial Area'.

Mahadevpur, K.R. Residential and commercial areas in Pura and Varthur areas have seen a substantial increase in guideline rates and value has also increased. In addition to this, the guideline price for agricultural land is in crores per acre. ₹13 crore per acre for agricultural land adjacent to Doddenekkundi Ring Road in Mahadevpur.

Guideline values are fixed in a separate category for apartments and villas. ₹ 2.86 lakh per square meter in Gandhinagar, ₹ 2.06 lakh in Sadashivnagar. ₹1.33 lakh in Jayanagar. Villas in Hersaghatta and Varthur area are of special category and cost more than ₹1 lakh per sq.m.

 15 to 30 percent increase: 

After five years, the government has revised the guideline values for immovable property, increasing it by 15 to 30 percent. According to real estate experts, the guideline price of residential plots has increased by 5 to 20 percent, the price of apartments by 10 to 15 percent, the price of villas by 10 to 20 percent and the price of agricultural land by 30 percent.

Where is the value of residential areas high?

 (per square meter)

  •  Sankey Road, Sadashivnagar; ₹3.02 lakh
  •  OTC Road Avenue – Nagartarpet Road; ₹2.84 lakh
  •  Jayanagar 4th Block 11th Main Road; ₹2.76 lakh
  •  Malleswar Margosa Road, 15th Avenue, 8th Main Road Junction; ₹2 lakh
  •  Hosur Road; ₹1.98 lakh
  •  Bannerghatta Main Road; ₹1.91 lakh
  •  Rajajinagar Dr. Rajkumar Road; ₹1.81 lakh
  •  HSR Layout BDA Complex Road; ₹1.75 lakh
  •  Rajajinagar Bashyam Circle; ₹1.75 lakh
  •  Basavanagudi Kanakapura Road; ₹1.66 lakh
  •  RPC Layout 1st Main Road; ₹1.6 lakh
  •  JP City 15th Avenue; ₹1.44 lakh
  •  RR Nagar Jayanna Circle; ₹1.2 lakh
  •  Nagarabavi Outer Ring Road; ₹90 thousand

 How much per acre of agricultural land?

  •  Around Doddanekkundi Ring Road; ₹13 crore
  •  Mahdepur Outer Ring Road; ₹12 crore
  •  Around Benniganahalli National Highway; ₹11.80 crore
  •  ITPCL; ₹11 crore
  •  Kundalahalli Junction to ITPL; ₹10.21 crore
  •  Kanakapura Road – Sarakki to Konnakunte; ₹9.99 crore
  •  Sarjapur Road; ₹9.88 crore
  •  B. Narayanpur Main Road; ₹9.51 crore
  •  Krishnarajpur National Highway; ₹9.4 crore
  •  Hagadur/ Hudi; ₹9 crore

ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...




Saturday, September 30, 2023

BBMP Elections: More Confusion

 Commencement of work in ward immediately after notification: Decision of aspirants

 BBMP Elections: More Confusion

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

 Bengaluru: Will the BBMP elections take place? This question, which has been frequently asked for two years, has not yet received a clear answer. Even though 225 wards out of 243 wards were the final notification, the confusion further increased.

 The corporator aspirants including Congress-BJP said that there is only a fifty-fifty chance of holding the election. Earlier it was called assembly election. Now, they are saying that BBMP elections can be held after the Lok Sabha elections are over.

 Last time, the aspirants had done a lot of work and expenses within their limits as the election would be held for 243 wards. However, they clearly says that, they will not do such an adventure this time.

 We will start work within the ward after the Election Commission issues a notification regarding the holding of the election. Until then we have no faith in anyone. All MLAs of the city are united in postponing the BBMP elections. The aspirants say that none of the remaining MLAs, except one or two, need a corporation election at the moment.

 Ward boundary confusion: 

Congress government has canceled 243 wards created when BJP was in power and notified 225 wards. The BJP's complaint is that the boundaries have been changed to facilitate the Congress aspirants. "Isn't it the same as what you have done in the past?" Congress asked. Thus, the possibility of this border dispute going to court again is high.

 Reservation Confusion Again:

Reservation of 225 wards under BBMP should be given to 10 categories. 24.10 per cent (54-55 wards) should be reserved for Scheduled Castes and Tribes, 34.17 per cent (77 wards) for Backward Class – A category (BCA) and 11 wards for Backward Class – B category.

Ward reservation should be finalized and notified. It has to be certified and issued when the government submits it to the court. The government has not yet accepted the caste report prepared for these castes and sub-castes. It should be approved by the cabinet and then submitted to the court. Court should accept it. Experts say that this process takes months.

 Castes belonging to backward classes should be notified and submitted to the Supreme Court. 17 states including Karnataka are yet to submit this report. After the Union Cabinet approves it, the President has to give his assent. He informed that the confusion will be solved only then.

 December 13 deadline!

 There is a rule that elections to local bodies cannot be held six months before or after the Lok Sabha elections. Thus, the BBMP elections are to be held by December 13 and the results are to be announced.

 Congress and BJP leaders are expressing mutual suspicion that they can go to court regarding ward allocation and reservation.

 Reservation final in two weeks: Ramalingareddy

 The government is ready to hold the BBMP elections within the first week of December. The reservation of wards will be finalized in another two weeks. The government has given many facilities and 'lucks' to the people. Transport Minister Ramalingareddy said that we are going to get the results of that and come to power in BBMP.

ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...



Friday, September 29, 2023

BSK, J.C. Road flyovers to ease congestion

 Project to facilitate vehicular traffic in the southern part of the city

BSK, J.C. Road: Two flyovers to ease congestion


Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

 Bengaluru: BBMP is planning to undertake two projects to facilitate traffic in the southern part of the city.

 An integrated flyover from Krishna Rao Park to Kanakapura Road, an underpass from Banashankari Market to Sarakki Junction has been launched. Apart from this, the construction of Elevated Corridor from Minerva circle to Hudson circle is also in progress.

 There is heavy traffic at Banashankari Junction now and it will increase further in the coming days. Raghunath Naidu, who was the Congress candidate from Padmanabhanagar Assembly Constituency, requested DCM that flyovers should be constructed at five or six junctions including this junction to enable signalfree traffic.

 On this request Deputy Chief Minister D.K. Shivakumar had inspected the place on August 18. He had directed the BBMP officials to prepare a Detailed Project Report (DPR). Accordingly, BBMP has invited tenders for the DPR of the project on September 25. There is an opportunity to submit the tender within October 3 and the tender process will be completed on October 9. DPR can be submitted within 30 days.

 BBMP engineers said that there is a plan to construct an integrated flyover from Krishna Rao Park, Tata Silk Farm Junction, Yediyuru Junction, Yediyuru Maternity Hospital Junction, JSS College Junction, Hunasemara Junction, Banashankari Temple, Kanakapura Road.

J.C. Road 'elevated corridor'!

 J.C. road 'Elevated Corridor' which was planned to be built under the amruthanagarotthan grant in the BJP government. For construction of road 'Elevated Corridor' Deputy Chief Minister D.K. Shivakumar has given approval on 6th September. Tenders have been called immediately and the project has been suggested to be implemented.

 Earlier there was opposition to the steel flyover. Therefore, some changes have been made in the DPR prepared earlier. A grant of ₹213 crore has been given for the 'Elevated Corridor' in the Amrita Urban Development Project, said the Planning Division Engineer.

 From Minerva Circle on J.C road an 'elevated corridor' will be constructed up to Hudson Circle. It is a two-way four-lane flyover. Minerva Circle, Bharat Talkies, Shivaji Talkies, Town Hall, LIC Head Office, Halasur Gate Police Station Junction and Hudson Circles will be signal free. This project was supposed to start in July last year.

From V.V Pura and RV Road Vehicles get over. They can get down to K.G. Road and Kasturaba Road. On other end from Nripatunga Road, vehicles get over to R.V. road to get off.

 J.C. Road flyover work was supposed to start in 2009 itself. Then the project amount was ₹86 crore. The state government had approved the scheme in 2013-14. An expenditure of ₹135 crore was approved for the steel flyover in the 2016 urban development plan. Now, the cost of the 'elevated corridor' will double.

ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...



Thursday, September 28, 2023

NPKL: Speed up Major Arterial Road works

 Construction of 35 Minor Bridge, 3 underpasses will be completed in another year

 NPKL: Speed up Major Arterial Road works

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

 Bengaluru: The work on the Major Arterial Road (MAR) connecting Mysore Road – Magadi Road passing through Nadaprabhu Kempegowda BDA Layout has gained speed.

 Many approval processes and tender approvals of the project, which had been stalled for many years, have been completed in the last six months, so the work of MAR has been accelerated.

 35 Minor bridges are to be constructed on MAR in Nadaprabhu Kempegowda BDA. BDA Commissioner Kumar Naik gave permission for it in March and already 15 short bridges have been completed. 10 short bridges are in final stage and rest will be completed in another five months.

 Underpasses are to be constructed at 2.90 km, 5.10 km and 9.70 km in MAAR. These connect the barangay roads to the main road. The contract for this work was confirmed by agreement deed dated 14th September. BDA engineers informed that the construction work of underpasses is also going on and everything will be completed in one year.


 "Commissioner Kumar Naik has given speed to the stalled files and has indicated that no work for providing infrastructure should be delayed. He said that his orders and necessary permissions were received quickly and all the infrastructure works in Nadaprabhu Kempegowda area have been speeded up.

 Case four: Land acquisition proceedings of an area of about 1 km road on a 10.75 km MAR are in court. About 3 km of the 9.75 km road has been completed. Rest of the road development work is in progress. It will be completed in another year, BDA engineers said.

The construction of MAR will provide connectivity to Mysore Road and Magadi Road and will also connect Sulikere-Ramasandra, Kenchapura, Kannahalli villages. Besides, Nadaprabhu will provide connectivity to 56 roads of Kempegowda Barangay.

 Where is the short bridge?: Kommaghatta, Bheemanakuppe, Kannalli, Ramasandra, Kenchanpur, Sulikere, Kodigehalli, Challaghatta.


  •  10.75 km MAR length
  •  ₹ 450 crore Estimated project cost
  •  100 meter wide road
  •  9 Block connecting access road
  •  35 minor bridges at a total cost of ₹26.91 crore
  •  3 underpasses at a construction cost of ₹39.31 crore
  •  Construction cost of 1 rail underbridge is ₹38.42 crore

ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...

ಎನ್‌ಪಿಕೆಎಲ್‌: ಪ್ರಮುಖ ರಸ್ತೆ (ಎಂ ಎ ಆರ್) ಕಾಮಗಾರಿಗೆ ವೇಗ



Saturday, September 23, 2023

POP idol: BBMP hiding the truth

 Violation of Prohibition Order: Officers who have not taken action despite being pop idol immersion

 POP idol: BBMP hiding the truth

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

 BENGALURU: The use of POP idols, which is banned across the state, is being immersion before the authorities.  A case has not been registered in this regard.  The information that such idols are being immersion is also being hidden now.

 BBMP had officially informed that more than 10 thousand POP idols were immersed on the first day of Ganesha festival.  The question was expressed by the citizens that 'how was it immersed even though there was a ban?'

 The Forest and Environment Department had issued an order prohibiting the manufacture, sale and immersion of any idols including POP Ganesha idols, Ganesha decorated with heavy metal colored chemical paint.  Manufacturing, selling and immersion of POP idols in violation of this order will be considered a punishable offence.  This offense is punishable by imprisonment for a minimum of one and a half years and a maximum of six years.

 However, on Ganesha festival, more than 10,000 POP idols were immersed in BBMP jurisdiction.  No one had taken any action.  At least one case was not registered.  This was questioned by environmental activists and citizens.  Thus, BBMP has kept the details of immersion of POP idols under wraps.

 1.19 lakh idols were immersed on Wednesday, the third day of Ganesha immersion.  But there is no detail of POP idols.  State Pollution Control Board officials, police, revenue and BBMP officials should have taken action against the sale, use and disposal of POP idols.  Without doing that, the information is hidden and all the immersion ones are depicted as clay idols.  Officials said that they have received a verbal instruction from the Forest Minister's office to do this.

ಕನ್ನಡದಲ್ಲಿ ಓದಲು ಇಲ್ಲಿ ಕ್ಲಿಕ್ ಮಾಡಿ...ಪಿಒಪಿ ಮೂರ್ತಿ

ನಿಷೇಧ ಆದೇಶ ಉಲ್ಲಂಘನೆ: ವಿಸರ್ಜನೆಯಾದರೂ ಕ್ರಮ ಕೈಗೊಳ್ಳದ ಅಧಿಕಾರಿಗಳು

ಪಿಒಪಿ ಮೂರ್ತಿ ಮುಚ್ಚಿಟ್ಟ ಬಿಬಿಎಂಪಿ

ರಾಜ್ಯದಾದ್ಯಂತ ನಿಷೇಧವಾಗಿರುವ ಪಿಒಪಿ ಮೂರ್ತಿಗಳ ಬಳಕೆ, ವಿಸರ್ಜನೆ ಅಧಿಕಾರಿಗಳ ಮುಂದೆ ನಡೆಯುತ್ತಿದೆ. ಆ ಬಗ್ಗೆ ಪ್ರಕರಣ ದಾಖಲಿಸಿಲ್ಲ. ಅಂತಹ ಮೂರ್ತಿ ವಿಸರ್ಜನೆಯಾಗುತ್ತಿವೆ ಎಂಬ ಮಾಹಿತಿಯನ್ನೂ ಇದೀಗ ಮುಚ್ಚಿಡಲಾಗುತ್ತಿದೆ.

ಗಣೇಶ ಹಬ್ಬದ ಮೊದಲನೇ ದಿನ 10 ಸಾವಿರಕ್ಕೂ ಹೆಚ್ಚು ಪಿಒಪಿ ಮೂರ್ತಿಗಳು ವಿಸರ್ಜನೆಯಾಗಿವೆ ಎಂದು ಬಿಬಿಎಂಪಿ ಅಧಿಕೃತವಾಗಿ ಮಾಹಿತಿ ನೀಡಿತ್ತು. ‘ನಿಷೇಧವಿದ್ದರೂ ಹೇಗೆ ವಿಸರ್ಜನೆ ಮಾಡಿಕೊಡಲಾಯಿತು’ ಎಂಬ ಪ್ರಶ್ನೆ ನಾಗರಿಕರಿಂದ ವ್ಯಕ್ತವಾಗಿತ್ತು.

ಪಿಒಪಿ ಗಣೇಶ ವಿಗ್ರಹಗಳು, ಭಾರಲೋಹ ಮಿಶ್ರಿತ ರಾಸಾಯನಿಕಯುಕ್ತ ಬಣ್ಣದಿಂದ ಅಲಂಕಾರ ಮಾಡಿದ ಗಣೇಶ ಸೇರಿ ಯಾವುದೇ ವಿಗ್ರಹಗಳ ತಯಾರಿಕೆ, ಮಾರಾಟ ಹಾಗೂ ನೀರಿನಲ್ಲಿ ವಿಸರ್ಜನೆ ಮಾಡುವುದನ್ನು ನಿಷೇಧಿಸಿ ಅರಣ್ಯ ಮತ್ತು ಪರಿಸರ ಇಲಾಖೆ ಆದೇಶ ಹೊರಡಿಸಿತ್ತು. ಈ ಆದೇಶ ಉಲ್ಲಂಘಿಸಿ ಪಿಒಪಿ ವಿಗ್ರಹಗಳ ತಯಾರಿಕೆ, ಮಾರಾಟ ಮಾಡಿದರೆ ಮತ್ತು ವಿಸರ್ಜಿಸಿದರೆ ಅದನ್ನು ಶಿಕ್ಷಾರ್ಹ ಅಪರಾಧ ಎಂದು ಪರಿಗಣಿಸಲಾಗುತ್ತದೆ. ಈ ಅಪರಾಧಕ್ಕೆ ಕನಿಷ್ಠ ಒಂದೂವರೆ ವರ್ಷ ಹಾಗೂ ಗರಿಷ್ಠ ಆರು ವರ್ಷಗಳ ಕಾರಾಗೃಹವಾಸ ಶಿಕ್ಷೆ ವಿಧಿಸಲಾಗುತ್ತದೆ ಎಂದು ಹೇಳಲಾಗಿತ್ತು.

ಆದರೆ, ಗಣೇಶ ಹಬ್ಬದಂದು 10 ಸಾವಿರಕ್ಕೂ ಹೆಚ್ಚು ಪಿಒಪಿ ಮೂರ್ತಿಗಳು ಬಿಬಿಎಂಪಿ ವ್ಯಾಪ್ತಿಯಲ್ಲಿ ವಿಸರ್ಜನೆಯಾಗಿದ್ದವು. ಯಾರೂ ಯಾವ ರೀತಿಯ ಕ್ರಮವನ್ನೂ ಕೈಗೊಂಡಿರಲಿಲ್ಲ. ಕನಿಷ್ಠ ಒಂದು ಪ್ರಕರಣವನ್ನೂ ದಾಖಲಿಸಿರಲಿಲ್ಲ. ಇದನ್ನು ಪರಿಸರ ಕಾರ್ಯಕರ್ತರು, ನಾಗರಿಕರು ಪ್ರಶ್ನಿಸಿದ್ದರು. ಹೀಗಾಗಿ, ಬಿಬಿಎಂಪಿ ಪಿಒಪಿ ಮೂರ್ತಿಗಳ ವಿಸರ್ಜನೆ ಮಾಹಿತಿಯನ್ನೇ ಮುಚ್ಚಿಟ್ಟಿದೆ. 

ಗಣೇಶವ ವಿಸರ್ಜನೆಯ ಮೂರನೇ ದಿನ ಬುಧವಾರ 1.19 ಲಕ್ಷ ಮೂರ್ತಿಗಳು ವಿಸರ್ಜನೆಯಾಗಿವೆ. ಆದರೆ ಪಿಒಪಿ ಮೂರ್ತಿಗಳ ವಿವರ ಇಲ್ಲ. ರಾಜ್ಯ ಮಾಲಿನ್ಯ ನಿಯಂತ್ರಣ ಮಂಡಳಿ ಅಧಿಕಾರಿಗಳು, ಪೊಲೀಸ್‌, ಕಂದಾಯ ಹಾಗೂ ಬಿಬಿಎಂಪಿ ಅಧಿಕಾರಿಗಳು ಪಿಒಪಿ ಮೂರ್ತಿಗಳ ಮಾರಾಟ, ಬಳಕೆ, ವಿಸರ್ಜನೆ ವಿರುದ್ಧ ಕ್ರಮ ಕೈಗೊಳ್ಳಬೇಕಾಗಿತ್ತು. ಅದನ್ನು ಮಾಡದೆ ಮಾಹಿತಿ ಮುಚ್ಚಿಟ್ಟು, ವಿಸರ್ಜನೆಯಾದವೆಲ್ಲ ಮಣ್ಣಿನ ಮೂರ್ತಿಗಳೇ ಎಂದು ಬಿಂಬಿಸಲಾಗಿದೆ. ಈ ರೀತಿ ಮಾಡುವಂತೆ ಅರಣ್ಯ ಸಚಿವರ ಕಚೇರಿಯಿಂದ ಮೌಖಿಕ ಸೂಚನೆ ಬಂದಿದೆ ಎಂದು ಅಧಿಕಾರಿಗಳು ತಿಳಿಸಿದರು.



Thursday, September 21, 2023

Lake encroachment: Tehsildars not ready for survey

 As per action plan directed by High Court, submission of list of 30 lakes by BBMP

 Lake encroachment: Tehsildars not ready for survey



Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

 Bengaluru: Even after three weeks, Tahsildars have not taken any action regarding the report submitted by BBMP engineers to clear encroachment of lakes.

 BBMP has implemented an action plan to clear encroachments in 159 lakes as directed by the High Court. So far 30 lakes have been listed at 10 lakes per week from the first week of September and sent to the respective Tehsildars.

 As per the action plan, the encroachment clearing process of 159 lakes should start in 16 weeks. Once the process is started, the eviction process should be completed within 70 days. September 5 was the first week, 10 lakes were listed and the process was started. After this, the encroachment of the lakes for the second and third week has been listed and submitted to the Tehsildar by the respective Executive Engineers of the BBMP Lakes Division.

 The Tehsildar has not started the process of encroachment list submitted on the first week. According to this report, the Tahsildar should have issued an order within seven days to identify the encroachment and conduct a survey. However, BBMP officials said that no such order has been issued so far for any lake in Entoo zone.

 District Collector Dayananda did not comment on the tehsildars not taking action to clear encroachment of lakes.

 Lakes in the weekly list

  •  First week (Sec. 5): Veerasagar lake, Bhattarahalli lake, Vengayyanakere, Srigandhad Kaval lake, Dasarahalli (Chokkasandra) lake, Mangammanapallya lake, Puttenahalli lake (near Brigade Millennium), Byrasandra lower lake, Nayandahalli lake, Kempambudhi lake.
  •  Second week (Sep.12): Kattigenahalli Lake, Amritahalli Lake, Rampur Lake, Chikkabellandur Lake, Hoskerehalli Lake, Boosegowdan Lake, Bagalgunte Lake, Dorekere, Kudlu Chikkakere – Anekal, Bairasandra – Chikkapet Lake.
  • Third Week (Sep.19): Agrahara Lake, Pattandur Agrahara Lake, Pattandur Lake, Halagevaderahalli Lake, Herohalli Lake, Abbigere Lake, Doddabidarakallu- Nagasandra Lake, Kodige Singhasandra Lake, Sanki Lake, Maestripalya Lake.


 Lake Management: Information in the app

 BBMP is preparing an APP that will provide information to the citizens about what works are going on in the lakes, what are the maintenance works, what time the cleaning works were carried out...

 This app is under development and data is being collected. May be final in another month. Officials said that the app is being developed at a cost of ₹10 lakh.

₹35 crore for Lakes Maintenance 

 ₹35 crore is being spent on maintenance works in 2023-24 in 174 lakes under BBMP. These works have been approved in the budget and the tender process will start now and end in November.

 Out of 174 lakes, 109 maintenance works have been decided to be undertaken, out of which tenders have already been invited for 96 works. Officials informed that the amount is ₹32.33 crore and tenders are being invited for 13 works for the remaining ₹2.66 crore.

 53 lakes in Mahadevpur zone, Bommanahalli – 42, R.R. Nagar – 33, Yalahanka – 24, Dasarahalli – 11, South – 5, East – 4 and 2 lakes in West zone are taken for the the annual maintenance work.