As per action plan directed by High Court, submission of list of 30 lakes by BBMP
Lake encroachment: Tehsildars not ready for survey
Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್
Bengaluru: Even after three weeks, Tahsildars have not taken any action regarding the report submitted by BBMP engineers to clear encroachment of lakes.
BBMP has implemented an action plan to clear encroachments in 159 lakes as directed by the High Court. So far 30 lakes have been listed at 10 lakes per week from the first week of September and sent to the respective Tehsildars.
As per the action plan, the encroachment clearing process of 159 lakes should start in 16 weeks. Once the process is started, the eviction process should be completed within 70 days. September 5 was the first week, 10 lakes were listed and the process was started. After this, the encroachment of the lakes for the second and third week has been listed and submitted to the Tehsildar by the respective Executive Engineers of the BBMP Lakes Division.
The Tehsildar has not started the process of encroachment list submitted on the first week. According to this report, the Tahsildar should have issued an order within seven days to identify the encroachment and conduct a survey. However, BBMP officials said that no such order has been issued so far for any lake in Entoo zone.
District Collector Dayananda did not comment on the tehsildars not taking action to clear encroachment of lakes.
Lakes in the weekly list
- First week (Sec. 5): Veerasagar lake, Bhattarahalli lake, Vengayyanakere, Srigandhad Kaval lake, Dasarahalli (Chokkasandra) lake, Mangammanapallya lake, Puttenahalli lake (near Brigade Millennium), Byrasandra lower lake, Nayandahalli lake, Kempambudhi lake.
- Second week (Sep.12): Kattigenahalli Lake, Amritahalli Lake, Rampur Lake, Chikkabellandur Lake, Hoskerehalli Lake, Boosegowdan Lake, Bagalgunte Lake, Dorekere, Kudlu Chikkakere – Anekal, Bairasandra – Chikkapet Lake.
- Third Week (Sep.19): Agrahara Lake, Pattandur Agrahara Lake, Pattandur Lake, Halagevaderahalli Lake, Herohalli Lake, Abbigere Lake, Doddabidarakallu- Nagasandra Lake, Kodige Singhasandra Lake, Sanki Lake, Maestripalya Lake.
Lake Management: Information in the app
BBMP is preparing an APP that will provide information to the citizens about what works are going on in the lakes, what are the maintenance works, what time the cleaning works were carried out...
This app is under development and data is being collected. May be final in another month. Officials said that the app is being developed at a cost of ₹10 lakh.
₹35 crore for Lakes Maintenance
₹35 crore is being spent on maintenance works in 2023-24 in 174 lakes under BBMP. These works have been approved in the budget and the tender process will start now and end in November.
Out of 174 lakes, 109 maintenance works have been decided to be undertaken, out of which tenders have already been invited for 96 works. Officials informed that the amount is ₹32.33 crore and tenders are being invited for 13 works for the remaining ₹2.66 crore.
53 lakes in Mahadevpur zone, Bommanahalli – 42, R.R. Nagar – 33, Yalahanka – 24, Dasarahalli – 11, South – 5, East – 4 and 2 lakes in West zone are taken for the the annual maintenance work.