BDA: 6 thousand flat in 3 years

 Current year expenditure for the project is ₹300 crore; Delay in some project by BDA engineers

 BDA: 6 thousand flat in 3 years

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

 Bengaluru: Bengaluru Development Authority (BDA) has come forward to provide more opportunities to housing aspirants. The plan to provide about six thousand flats in three years is under implementation.

 BDA has given high priority to housing projects and has decided to spend ₹298 crore in this year's budget for its initiation. The total cost is estimated at ₹1,500 crore. While many of these projects have been started, some of the projects are not progressing as expected. The file is pending disposal on the desk of the officers in charge of all the projects.

 Flats are being constructed in a total of 11 residential projects including Kondasanpur, Kommaghatta, Kaniminike, Dodtogur, Kudagere. Housing schemes are divided into Scheme-1 and Scheme-2. In Plan-1, some projects are progressing rapidly, while others are wasting a lot of time at the tender preparation stage.

 There is only one major project in plan-2. This is a project to build around 2 thousand flats in Kondasanpur, and ₹200 crore has been earmarked in this budget. However, the project is at a slow pace due to the laziness of the engineers. The project has to be completed in 30 months after the tender. Thus, senior BDA officials have suggested to start the project early. The complaint was expressed by the BDA officials themselves that the project is being delayed by the engineers from project supervision to implementation.

 BDA Commissioner Kumar Naik, Engineer Member Shanta Rajanna could not be reached for comment.

₹820 Crore: Around one thousand flats are being constructed in Kaniminike 1st and 2nd project, re-tenders have been called for this project. Konadasanpur-3, Valagerahalli, Dodtogur, Kudagere projects are being implemented at a cost of ₹820 crore. The Sonnenahalli project has cost a few crores and there is a restraining order in the court due to a land dispute. Engineers are slacking off on Housing Project-II where more flats are to be provided. From the in-charge engineers to the implementation engineers, no matter what you ask, they say 'no information'.

 Along with the residential projects, the construction of a commercial complex in Kondasanpur 3rd phase at a cost of ₹50 crore has been started. An expenditure of ₹5 crore is being spent this year, besides, the BDA is constructing a club house at Kaniminike.

 Hunnigere Villa is ready

 BDA has constructed 322 villas in Hunnigere. The project is almost complete and the order for price fixing sale is yet to come out. BDA officials said that it has been decided to sell these villas online under the 'first come first serve' scheme.

 The project is named as 'Puneeth Rajkumar Housing Complex'.

  • 298.97 crore: Expenditure in 2023–24 for housing projects
  •  ₹91.25 crore:  Housing Scheme–1
  •  ₹207.72 crore: Housing Scheme – 2

 Where is the housing scheme?

 Project; flats; Expenditure (in 2023–24)

 Hunnigere Villa; 322 ; ₹15.50 crore

 Kondasanpur Phase-3; 500; ₹8 crore

 Valagerahalli Phase-7; 200; ₹6 crore

 Dodtogur; 500; ₹10 crore

 Kuduregere; 500 ; ₹25 crore

 Kaniminike – 1 BHK;608;₹6 Crore

 Kaniminike – 2 BHK;384;₹8 Crore

 Sonnenahalli; 210; ₹5 crore

 Konadasanpur Residential Houses Phase-I; 1,900; ₹200 crore

 Kommaghatta NPKL Phase-I; 600; ₹3.48 crore

Kommaghatta NPKL Phase-2; 600; ₹4.24 crore