Saturday, June 3, 2023

Ejipura flyover: Delay again by BBMP

Fourth time tender; Delay in send to Government for approval

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

Bengaluru: The BBMP, which has been called for the fourth time for the pending work of the Ejipura flyover, has not submitted the tender to the government for approval despite being told four times by the transport minister.

 Tenders were invited for the fourth time on March 1 for the pending work of Ejipura flyover. Technical bids were opened on 17th and negotiations were held with the sole bidder. It has been retained as unfinished. However, on the same occasion, the High Density Corridor tender, which was called on March 17 and costing ₹270 crore, was approved on March 23 and the work orders was also given.

 In 2017, the work of the Ejipura flyover started and the case was taken up in the High Court due to the delay of the contractor. The lease was canceled on March 9, 2022. The High Court warned the BBMP that it should call for tenders again in three months and start the work. Even so, BBMP has not yet completed the tender process of BBMP.

The government had instructed to cancel the tender process as the bid was higher than the stipulated amount. Then a fresh tender was called. Two contractors had bid. One of them was not qualified. A request has been made to reduce the amount recorded by him. After they agree to it, it is sent to the government. From there the work will be started after getting the approval. As this is an ongoing work, the Election Code of Conduct will not stand in the way," BBMP officials had told in March. However, despite the beginning of June, the file has not been submitted to the government.

 The local people are in distress as the pending work of Ejipura flyover is not completed. We also protested with MLA Ramalingareddy. Now he is a minister. Rajendra Babu, president of Koramangala ST Bed Residents' Welfare Association, demanded that the work be completed soon.

 Scrutiny: 

'Tender scrutiny is going of the pending work of Ejipura flyover is going on' said BBMP Engineer in Chief Prahlad.

Told to Chief Commissioner but no action: Ramalingareddy

 The tender for the pending work of Ejipura flyover has been called for the fourth time and all the technical processes have been completed. I told Chief Commissioner Tushar Girinath and Engineer in Chief Prahlad four times to send it to the government for final approval. They are still counting time," said Transport Minister Ramalingareddy.

 The BJP government did not continue the pending work of the Ejipur flyover because of its hatred towards us. We have promised to continue this work as soon as our government comes and finish it in 12 months. But, BBMP officials are not responding to this. Action will be taken against them. He said that the tender will be approved and the work will be started immediately.