'Bengaluru Smart City': Speed ​​in the final phase

June 23 Center deadline; Full confidence of officials in April itself

Kere Manjunath ಕೆರೆ ಮಂಜುನಾಥ್

Bengaluru: While officials are confident that all the 'Bengaluru Smart City' projects will be completed by the end of April, a couple of works will continue till the Centre's deadline. It is doubtful that the car parking project will start even after the deadline

The deadline given by the Center to complete the implementation of 'Smart City' projects will end on June 23. Bengaluru Smart City Limited has undertaken a total of 44 projects, of which 30 have been completed so far. Out of the remaining 14 projects, 13 projects have completed an average of 80% work, while one work has not yet started.

 Inspection of factories is going on every week under the leadership of Smart City Project Managing Director Srinivas. Intimation is being sent to speed up the work. All the contractors have been given a deadline of March end to complete the work.

 K.R. The development, including the underpass and glazing of the Market Commercial Centre, is almost complete. Meat market reconstruction project abandoned. The work of developing the existing market has now been given a high speed.

 Development of the new designs at Cubbon Park is 90 percent complete. However, 25 percent of the work on the hall and auditorium in the Jawaharlal Nehru Planetarium is pending. One block has been completed and work on the other is now in full swing.

 Two roads in Package B in the development of 32 roads in Tendersure are yet to be completed. The road and avenue road from Queen's Road to Russell Market have not been completed. The Avenue Road work has been delayed as the BWSSB route has to be changed, and now it has been given to the Sewerage Board to complete the work. They will be completed by April, said Chief Engineer of Bangalore Smart City Project Doddaiah.

One number, one portal...

Only 80 percent of the implementation of the ICCC system, which provides solutions to all citizens' problems at a single platform, has been completed. Citizens can register all complaints including BBMP, BDA, BESCOM, BWSSB, Police on a single number or portal. This ICCC, which works to solve it, gives its real information to the citizens. Officials said that all the departments have been contacted for this and this center is being implemented in BBMP.

BBMP has not handed over the land!

The construction work of the multi-storey car park at Gandhibazar has not yet started. BBMP has not handed over the land. Temporary work has started there. If the traders there are shifted and the place is handed over to us, the work will be started. The tender for this has been completed and the work is expected to be completed in 11 months. If BBMP does not hand over the land within our deadline, the project will be taken over by them," said Susheelamma, Joint Managing Director of Bangalore Smart City Project.

A couple of works may be completed in April. Apart from that, everything else will be completed by March itself

Srinivas, Managing Director, Smart City

 ₹932.10 crore: Overall cost of the project

 ₹673 crore: Release of funds